Completed Date
Could be used to capture the Completion Date for the project or task. On a number of reports, the project or task is considered Completed only if this field is populated.
Frozen from further Modification
When using the Unanet Billing functionality, there are conditions when the Completed Date is no longer modifiable.
When you have a fixed price item at the project level that is configured to Bill on Completion (see Project Billing>>Fixed Price), and billing transactions (see note below) have been generated for that item, then the % Complete and Completed Date fields will no longer be modifiable.
Note Billing transactions include:
Journal transactions with category UNBILLED generated as a result of running Billing & Revenue post that included the given fixed price item, or
BILLED journal transactions for that fixed price item resulting from running the Billing & Revenue post, adding those UNBILLED journal transactions to an invoice, and completing the invoice.
Timesheet Implications
If you have a project configured with the Enforce Project/Task Dates option enabled, projects will not be available for time entry beyond the Completed Date (should one be supplied).