Unposted Billings and Revenue

The values appearing in the Unposted Billings and Unposted Revenue sections on the Post >> List screen reflect the sum of the projected journal entry transactions that would result from posting a particular project (as if the post had occurred).

Clicking on any of the values in the Unposted Billings and Unposted Revenue columns will display a Billing and Revenue Details report showing the projected journal entry transaction details that make up the amounts displayed on this List screen.

See the Cost Plus Post Process and T&M / Fixed Price Post Process details to understand specifically how pre-billed labor, labor, expense and fixed price items are qualified to be included in a post process.

What do these amounts include?

 

General Assumptions:

 

Only those time and expense actuals that have reached the LOCKED or EXTRACTED will be considered.

No data that has previously participated in a post will be included.

Item Date <= Include Actuals Through date

 

For Cost Plus projects (Billing Type = CP):

Because we are dealing with Cost Plus projects, the project type associated with project / task and time and expense actuals does not come into play, that is, the cost for all actuals are considered.

Because the Unbilled and Recognized Revenue amounts use the same labor and expense cost values (as detailed below) the only difference you would see in the values for these two entries would be the result of using different Cost Plus Bill Rate and Cost Plus Recognition Rate values as defined on the Admin >> Setup >> Billing screen.

 

For Non-Cost Plus projects (Billing Type = TM or FP):

For TM & FP projects, we will consider the project type that time and expense actuals have been charged against and only consider those charged to billable project types.