Reports - Project Accounting - Earned Value Line Chart

Overview

This chart can be run to provide a graphical representation of project / task earned value information in a weekly, monthly or yearly interval.    

Click Through for Details

This chart does not currently support any click through capabilities.

Roles

This report is available to users having any of the following roles:  Administrator and P&R Administrator.  

Certain Project Administrator roles can have access to this report under the following conditions:

 

User has Bill Rate Manager Role User has Cost Rate Manager role Allow Project Cost Reporting for Non-Cost Rate Managers (unanet.non_cost_mgr.allow_project_cost_reporting) property enabled Report Access
Yes No Yes Can see and run report
Yes Yes Yes or No Can see and run report
No No Yes Can see report but cannot run it
No Yes Yes or No Can see and run report

 

Note: The Project Administrator roles or  "project oriented" roles referred to in the property description are the ones listed below:

 

License

This report is available with the Project Portfolio family of licenses.

 

Topics covered on this help page include:

 

You may also be interested in:


Selection Criteria

Field Descriptions (click on a link below for additional information)

 

 


Example Chart Output

This report will use the information available on the Budget Snapshots (when available), otherwise the current project/task budget information will be used.  When using the Budget Snapshot information, the entry used for each data point will be the entry having the minimum date greater than the end date of that period of interest.